Firth Park Academy is one of 64 academies within Academies Enterprise Trust (AET). The secondary school has over 1,300 pupils and an OFSTED rating of ‘Good’.
*AET was established in 2008 and now educates over 35,000 pupils and employs over 6,000 highly committed staff. One of their values is to create an environment which is highly participative and aspirational, where every student has the opportunity to develop the abilities they need to lead positive and fulfilling lives.
The Challenge
AET has four key finance priorities, one of which is to spend wisely. Coupled with the usual budgetary constraints experienced within education, operational savings needed to be made. The installation of LED lighting offered a way to improve the school environment and make significant annual savings. Academies Enterprise Trust made contact with LASER to find out more about the LED lighting framework.
The school’s lighting was predominantly old, high energy fluorescent style fittings, expensive to run with high maintenance costs. Several corridors were over lit due to the high quantity of fittings installed and lighting was extremely harsh. The challenge was to design an LED lighting system that could quickly pay for itself through savings in electricity bills whilst providing softer lighting that still creates a bright, clean look.
The Solution
Together LASER, AET and Firth Park Academy designed a lighting installation that not only produced financial savings, but also met the desired outcomes of quality and price. LASER surveyed the building, specified equipment from suppliers on the framework, and calculated accurate project costs, savings and return on investment. We used all of the information gathered to assist AET in making a bid to Salix Finance Ltd.
The savings in electricity usage needed to be utilised to pay back the cost of the project within an eight year period to satisfy funding criteria; the LASER design and specification calculated payback in only seven years.
The installation was fully completed in four weeks using a contractor from LASER’s framework with oversight from LASER’s team to ensure the project stayed on schedule and to a high standard.